Legend
Funding & appropriation
Procurement
Consultant onboarding
Phase 1 — broad outreach
Phase 2 — focused outreach
Gap & funding analysis
Draft review
Final plan
Today

Key Milestones & Deliverables

Timeframe Phase Key Activities Deliverables
Jul 2026 Funding Appropriate Park & Greenway Maintenance funds from CIP into Operational Approved budget transfer; Maintenance baseline established
Jun – Jul 2026 Procurement Release RFP; run appropriation process concurrently to compress pre-engagement window Published RFP; Proposals received
Aug – Sep 2026 Onboarding Consultant NTP; develop detailed work plan and community engagement plan; internal alignment meetings Signed NTP; Work Plan; Engagement Plan; Stakeholder Contact List
Oct 2026 – Feb 2027 Phase 1 Combined outreach w/ Vision Zero & Open Space; community events, online surveys (incl. late-night), booths, neighborhood presentations Survey data; Event reports; Demographic analysis; Preliminary gap identification
Q2 – Q4 2027 Phase 2 Pop-ups at facilities; roundtables with interest-holder groups (bicycle, homebuilders, DDA, Lions Club, athletic groups); random sampling Interest-holder input reports; Use-pattern data; Prioritized gap list; Draft funding framework
Q1 2028 Draft Share Master Plan draft with interest-holders; collect feedback; reconcile with Envision Longmont, Transportation Master Plan, Total Park Health Draft Master Plan; Stakeholder review comments log; Revision matrix
Q3 2028 Final Plan Adopt Final Master Plan; launch public-facing communications (website, social, newsletters); align with Longmont Indicators; set 3- & 5-year check-in milestones Adopted Final Plan; Public summary materials; Indicators alignment report; Review schedule